9.4 Consider Approval of Emergency Yermo Emergency Pathway, Electrical and Communications Repairs with Bradley General Building.
|
Strategic Plan:
|
|
Enclosure
|
SVUSD BGB Yermo Emergency TM Proposal v1.pdf
|
File Attachment:
|
|
Summary:
|
During the Yermo School Gymnasium construction, an unknown underground conduit was discovered. This conduit contained communication cabling for the middle school portables. It was determined by the contractor that the conduit conflicted with the gym’s footing locations, requiring rerouting.
During the removal of the conduit, an unseen electrical and fire alarm pathway was damaged, causing a power outage to the school office. BGB responded immediately, provided a backup generator, and completed the necessary electrical and communication repairs. All power and communication services have been fully restored.
|
Funding:
|
General Fund: $42,575.00
|
Recommendation:
|
It is recommended that the Governing Board of Trustees approve the emergency pathway, electrical, and communications repairs with Bradley General Building, as presented.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Robert Saffel - Senior Director of Technology, Maintenance and Operations
|
|
Signed By:
|
|
Robin Schreiner - Senior Director, Business Services
|
|
Signed By:
|
|
Marc Lacey - Assistant Superintendent, Administrative Services
|
|
Signed By:
|
|
Jesse M. Najera - Superintendent
|
|
|
|
|
|
|
|