10.1 Consider Approval for Concrete Repair Work at the District Office with Bradley General Building
|
Strategic Plan:
|
|
Enclosure
|
BGB SVUSD Concrete Repair at DO Quote.pdf
|
File Attachment:
|
|
Summary:
|
Approximately 1,400 square feet of concrete in the District Office Complex needs replacement. In the main traffic area, frequent vehicle and bus traffic has caused sections of the concrete slabs to chip and deteriorate, creating hazards like loose concrete fragments and potholes.
The damaged concrete will be removed and replaced with 5-inch thick, 3,500 psi Buckeye fiber-reinforced concrete, and finished to match the surrounding areas.
|
Funding:
|
Maintenance: $23,000.00
|
Recommendation:
|
It is recommended that the Governing Board of Trustees approve the concrete repair work at the District Office with Bradley General Building, as presented.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Robert Saffel - Senior Director of Technology, Maintenance and Operations
|
|
Signed By:
|
|
Robin Schreiner - Senior Director, Business Services
|
|
Signed By:
|
|
Marc Lacey - Assistant Superintendent, Administrative Services
|
|
Signed By:
|
|
Jesse M. Najera - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Lynn McKee Moved, Member Brian Boatwright seconded to approve the Original motion 'It is recommended that the Governing Board of Trustees approve the concrete repair work at the District Office with Bradley General Building, as presented.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 4 Nay: 0. | The motion Carried 4 - 0 |
|
|
|
|
|
|